Client:
Lend Lease / Excell Gray Bruni
Description:
Harpley extension consists of two steel boardwalk bridges that creates a pedestrian walkway over that will connect the new town centre with the new manmade lake.
Works involved:
-Piling and detailed excavations.
-Formwork, Reinforcement and Concrete of piers, footings and bridge abutments.
-Formwork, Reinforcement and Concrete of 100 creek wall.
-Fabrication of steel bridges, over 150m combined. Shopdrawn and fabricated in house.
-Crane works
Equipment and efficiencies utilised:
Bridgecon have self-fabricated& have shop drawn both steelbroadwalk bridges, which will be installed using our 100T crane.
Site & project engineer, site foreman dedicated to site with presents of company owner for over 85% of the project to ensure coordination/communication and consistency of work quality was kept to the highest standard. Bridgecon completed our own inspection & test plans on our works to ensure everything was completed to a high standard to satisfy Vic roads standards.
Plant used on site:
– Inhouse Survey
– Inhouse formwork and temp works
– In house scaffold access
– 100T crane
– Franna cranes
– 14 & 35 tonne excavators
– Tipper trucks, rollers, materials handlers, utility vehicles and service vehicles
– Piling rigs
Project value: $4m+