Client:
 Lend Lease / Excell Gray Bruni
Description:
 Harpley extension consists of two steel boardwalk bridges that creates a pedestrian walkway over that will connect the new town centre with the new manmade lake.
 
 Works involved:
 -Piling and detailed excavations.
 -Formwork, Reinforcement and Concrete of piers, footings and bridge abutments.
 -Formwork, Reinforcement and Concrete of 100 creek wall.
 -Fabrication of steel bridges, over 150m combined. Shopdrawn and fabricated in house.
 -Crane works
Equipment and efficiencies utilised:
 Bridgecon have self-fabricated& have shop drawn both steelbroadwalk bridges, which will be installed using our 100T crane.
 Site & project engineer, site foreman dedicated to site with presents of company owner for over 85% of the project to ensure coordination/communication and consistency of work quality was kept to the highest standard. Bridgecon completed our own inspection & test plans on our works to ensure everything was completed to a high standard to satisfy Vic roads standards.
Plant used on site:
 – Inhouse Survey
 – Inhouse formwork and temp works
 – In house scaffold access
 – 100T crane
 – Franna cranes
 – 14 & 35 tonne excavators
 – Tipper trucks, rollers, materials handlers, utility vehicles and service vehicles
 – Piling rigs
Project value: $4m+
 